18 August 2021 | IMPORTANT NOTICE

x

In line with Ministry of Health guidance, our staff are currently working remotely. They remain available to assist and it is business as usual. However, we ask that wherever possible you contact us online or by email to registrar@buildingdisputestribunal.co.nz.

If you need to courier documents, please contact our Registry staff in the first instance to confirm the appropriate delivery details.

He waka eke noa.

Apply Now

Want to apply for Adjudication?
Application Form
Important information

Below you will find some important information you need to know before applying for adjudication. Please take a minute to read through this page carefully before making your application.

The Notice of Adjudication

The first step in the process is to serve a Notice of Adjudication on the other party or parties to the dispute – these will be the other parties to the construction contract under which the dispute has arisen.

You may also choose to serve the Notice of Adjudication on the owner of the construction site where the owner is not a party to the construction contract and you wish to seek a determination of that owner’s liability under section 30(a) and/or approval for the issue of a charging order under section 30(b).

Applying to the Building Disputes Tribunal

The Building Disputes Tribunal (BDT) is an authorised nominating authority (ANA) under the Construction Contracts Act 2002 (the Act).

Any party to a dispute arising under a construction contract is entitled to apply to us for the appointment of an adjudicator. There is no requirement to try to agree on the identity of the adjudicator with the other party (although of course you are also entitled to do so). Instead, you can apply directly to BDT and we will appoint an appropriately skilled and experienced adjudicator for your case typically within one working day. BDT does not charge the parties a fee to make that appointment.

PLEASE NOTE: an application for appointment of an adjudicator must be made in the period between and including two to five working days after the notice of adjudication is served on the other parties to the adjudication (ie barring the occurrence of any statutory non-working days – if the notice is served on a Monday you cannot make your application to BDT until the Wednesday, Thursday or Friday of that week or the Monday of the following week – if the notice is served on a Friday you cannot make your application to BDT until the following Tuesday, Wednesday, Thursday or Friday).

 

Cost certainty for resolving building and construction disputes: Extension to the BDT Adjudication Low Value Claim Scheme

By Belinda Green.   One of the main barriers to dispute resolution is cost: no one wants to risk spending more than the amount they recover. With inflation and construction costs always on the rise, BDT is extending its Low Value Claim (LVC) Scheme for...

Construction Contracts – Enforcement of Debts Due and Mandatory Alternative Dispute Resolution Clauses

By Melissa Perkin. The recent High Court decision in Hellaby Resources Services Limited v Body Corporate 197281 [2021] NZHC 554 is of particular interest in the construction sector for several key reasons: it is a rare example where a stay of enforcement of summary...

The Enforceability of Liquidated Damages Clauses

Author: Melissa Perkin  Liquidated damages clauses, a common feature of construction contracts, stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered. A recent United Kingdom decision of the...

Building and Construction Under COVID-19 Alert Level 4

For information and guidance on what building and construction work can be done at Alert Level 4: ·       Health and Safety protocols at different alert levels, visit CHASNZ COVID-19 and working at the current alert level (chasnz.org); and ·       COVID-19 guidance...

Class-action lawsuit against Harditex cladding fails

By Melissa Perkin.  A second class-action lawsuit[1] brought by a group of 144 homeowners whose homes were clad in Harditex fibre-cement cladding, has failed. The homeowners alleged that Harditex manufacturer James Hardie, between 1987 – 2005, knowingly sold defective...

What types of disputes can be referred to adjudication?

The types of dispute that can be referred to adjudication are listed below:  Default liability claim These are claims for technical non-compliance with the payment regime under the Act. Where a valid payment claim has been served by a payee on a payer and the payer...

Proposed Changes to the Construction Retentions Regime

Author: Hannah Stanley, Building Disputes Tribunal Registrar Despite the introduction of the retentions regime into the Construction Contracts Act 2002 (the Act) in 2017[1], many subcontractor retentions have still been left unprotected and various gaps in the...

Show Me the Money: Seven Things to Remember When Preparing a Payment Claim

By Amy McDonald Are you still waiting on an invoice to be paid that you sent ages ago? Have you done all the work but have nothing to show for it? Unpaid invoices can have a devastating impact on builders and subcontractors. Fortunately, the Construction Contracts Act...

Experts’ duties and conflicting interests – Secretariat Consulting Pte Ltd v A Company

By Belinda Green. Experts may look to amend their terms of engagement, as the English Court of Appeal finds a conflict of interest clause applied to a global brand, despite involving separate experts in different locations, contracting via separate legal entities....

Payment Claims: using Xero to send out your invoices? Don’t forget the important notice

By Catherine Green.   Do you use Xero to send out your invoices? Make sure they are compliant payment claims under the Construction Contracts Act 2002 (Act). The default payment regime under the Act is an efficient and effective way of getting your invoices paid....