18 August 2021 | IMPORTANT NOTICE

x

In line with Ministry of Health guidance, our staff are currently working remotely. They remain available to assist and it is business as usual. However, we ask that wherever possible you contact us online or by email to registrar@buildingdisputestribunal.co.nz.

If you need to courier documents, please contact our Registry staff in the first instance to confirm the appropriate delivery details.

He waka eke noa.

Low Value Claim Scheme

A fixed fee scheme providing cost certainty
Apply Now
We understand that the cost of having building or construction disputes resolved, or uncertainty about those costs, prevents many people from recovering money that they are properly entitled to be paid under building and construction contracts and reluctant payers often use that situation to their advantage. This is particularly so where the amount in dispute is relatively small by industry standards – claims for less than $100,000 including GST – and those payers assume that the payee will take no steps to recover the unpaid amount because the cost and bother of doing so outweighs the benefit. To redress that situation, the Building Disputes Tribunal (BDT) provides a fully administered fixed fee adjudication service for Low Value Adjudication Claims (LVC’s) of limited complexity. This scheme is aimed at providing parties to construction disputes with certainty as to the cost of taking a dispute to adjudication so that parties can make informed and considered commercial decisions as to whether to proceed down the adjudication pathway. This unique service ensures that the cost of having a low value claim resolved by adjudication is not disproportionate to the amount in dispute. Alternatively, parties are welcome to refer monetary claims for less than $100,000 to adjudication under our General Claim Service in which case the adjudicator’s fees and expenses will be calculated according to the time engaged on the duties of the adjudication by the adjudicator together with any expenses incurred by the adjudicator in the execution of those duties.
Fixed Fees
The table below sets out the applicable fixed fee. A notice of acceptance of appointment as adjudicator will not be served on the parties to the adjudication by BDT until the parties have paid (in clear funds) into BDT’s trust account the fixed fee as security for the adjudicator’s fees and expenses. The adjudication fees (inclusive of GST) as follows:
Code Amount of claim Fee Conditions
LVC5 ≤ $4,999.99 $1,500.00 Claim limited to 3 items at issue*. Documents that Claimant may file in support of the claim limited to: Notice of Adjudication, Adjudication Claim, and Contract Documents together with 15 single sided A4 pages (font size no less than 12) of submissions and evidence in relation to the claim and the matters at issue. No conference of the parties or inspection of construction work is included in the fixed fee. Limited reasons only provided
LVC10 $5,000.00 ≤ $9,999.99 $ 2,500.00 Claim limited to 3 items at issue*. Documents that Claimant may file in support of the claim limited to: Notice of Adjudication, Adjudication Claim, and Contract Documents together with 15 single sided A4 pages (font size no less than 12) of submissions and evidence in relation to the claim and the matters at issue. No conference of the parties or inspection of construction work is included in the fixed fee.
LVC20 $10,000.00 ≤ $19,999.99 $ 3,750.00 Claim limited to 3 items at issue*. Documents that Claimant may file in support of the claim limited to: Notice of Adjudication, Adjudication Claim, and Contract Documents together with 20 single sided A4 pages (font size no less than 12) of submissions and evidence in relation to the claim and the matters at issue. No conference of the parties or inspection of construction work is included in the fixed fee.
LVC30 $20,000.00 ≤ $29,999.99 $ 5,000.00 Claim limited to 3 items at issue*. Documents that Claimant may file in support of the claim limited to: Notice of Adjudication, Adjudication Claim, and Contract Documents together with 30 single sided A4 pages (font size no less than 12) of submissions and evidence in relation to the claim and the matters at issue. No conference of the parties or inspection of construction work is included in the fixed fee.
LVC40 $30,000.00 ≤ $39,999.99 $ 6,250.00 Claim limited to 3 items at issue*. Documents that Claimant may file in support of the claim limited to: Notice of Adjudication, Adjudication Claim, and Contract Documents together with 40 single sided A4 pages (font size no less than 12) of submissions and evidence in relation to the claim and the matters at issue. No conference of the parties or inspection of construction work is included in the fixed fee.
LVC50 $40,000.00 ≤ $49,999.99 $ 7,500.00 Claim limited to 3 items at issue*. Documents that Claimant may file in support of the claim limited to: Notice of Adjudication, Adjudication Claim, and Contract Documents together with 50 single sided A4 pages (font size no less than 12) of submissions and evidence in relation to the claim and the matters at issue. No conference of the parties or inspection of construction work is included in the fixed fee.
LVC60 $50,000.00 ≤ $59,999.99 $ 8,750.00 Claim limited to 3 items at issue*. Documents that Claimant may file in support of the claim limited to: Notice of Adjudication, Adjudication Claim, and Contract Documents together with 60 single sided A4 pages (font size no less than 12) of submissions and evidence in relation to the claim and the matters at issue. No conference of the parties or inspection of construction work is included in the fixed fee.
LVC80 $60,000.00 ≤ $79,999.99 $ 10,000.00 Claim limited to 3 items at issue*. Documents that Claimant may file in support of the claim limited to: Notice of Adjudication, Adjudication Claim, and Contract Documents together with 80 single sided A4 pages (font size no less than 12) of submissions and evidence in relation to the claim and the matters at issue. No conference of the parties or inspection of construction work is included in the fixed fee.
LVC100 $80,000.00 ≤ $99,999.99 $ 12,000.00 Claim limited to 3 items at issue*. Documents that Claimant may file in support of the claim limited to: Notice of Adjudication, Adjudication Claim, and Contract Documents together with 100 single sided A4 pages (font size no less than 12) of submissions and evidence in relation to the claim and the matters at issue. No conference of the parties or inspection of construction work is included in the fixed fee.
*The number of items at issue that may be dealt with under the fixed price LVC service is strictly limited to three, ie a total number of issues in the claim of three variations, or three items of allegedly defective work, or extension of time for one event and two variations etc. PLEASE NOTE: FOR CLAIMS IN EXCESS OF $100,000 AND/OR FOR THOSE CLAIMS THAT DO NOT FIT THE CRITERIA FOR LVC’s PLEASE SEE INFORMATION ON FEES FOR GENERAL CLAIMS 
Conference of the parties and/or inspection of construction work or any other thing to which the dispute relates, at the request of any party or at the Adjudicator’s discretion (the additional fee for a conference and/or inspection is payable to the Tribunal prior to release of the Adjudicator’s determination)
Fee: $750.00
Plus mileage/travel expenses
In the event that a claim or response presents undue complexity, or the submissions and evidence submitted in support of the claim exceed the permitted number of documents notwithstanding the low value of the claim or the limited number of matters at issue, or where two or more adjudication claims are consolidated, the Tribunal may, at its sole discretion, decline to provide the adjudication on a fixed fee basis under the LVC scheme. In that event, the Tribunal will advise the parties accordingly and the adjudication will simply revert to a General Adjudication and the cost of the adjudication will be determined by the time the adjudicator is required to expend on the duties of the matter, together with any expenses incurred by the adjudicator in the execution of those duties. In almost every case, the claimant will pay the security amount required to secure the appointment of the adjudicator immediately following service of the notice of adjudication when making an application for the appointment of an adjudicator. In such cases the claimant will, in its notice of adjudication, and subsequently in its adjudication claim, seek a determination from the adjudicator that the respondent, or any other party to the adjudication, is liable to meet the adjudicator’s fees and expenses and to reimburse the claimant for the security paid in such proportions as the adjudicator determines. When the Tribunal serves the adjudicator’s notice of acceptance on the parties, the Registrar will invite the respondent to contribute an equal share of the amount paid as security by the claimant on the basis that the Act contemplates that the parties will bear their own costs and expenses and meet the adjudicator’s fees in equal proportions unless the grounds in sections 56(1) and 57(4) are made out. In the event that the respondent pays that amount, the Tribunal will immediately issue the respondent with a receipt and refund the claimant in that same amount leaving the adjudicator to ultimately determine the issue of costs as between the parties.

Leaky Home Case: Failure to obtain a building report results in reduction of damages for contributory negligence

By Melt Strydom. Apportionment for contributory negligence allows a court to share the responsibility between parties in circumstances where the test for causation and remoteness of damage justifies it. It doesn’t mean a respondent will not be held liable for...

Do payment claims for retention money ‘fit’ with the standard terms of contract in New Zealand?

By Maria Cole The New Zealand Construction Contracts Act 2002 (CCA) does not explicitly state that payment claims can be used to recover retention money. That said, it is clear the 2015 amendments to the definition of a ‘payment’ under the CCA are broad enough to...

Resolving Construction Disputes – Is Adjudication a Good Option?

By Natalia Vila.   With few exceptions, the Construction Contracts Act 2002 (the Act) applies to every construction contract relating to construction work carried out in New Zealand. Statutory adjudication under the Act is the most commonly used dispute...

Cost certainty for resolving building and construction disputes: Extension to the BDT Adjudication Low Value Claim Scheme

By Belinda Green.   One of the main barriers to dispute resolution is cost: no one wants to risk spending more than the amount they recover. With inflation and construction costs always on the rise, BDT is extending its Low Value Claim (LVC) Scheme for...

Construction Contracts – Enforcement of Debts Due and Mandatory Alternative Dispute Resolution Clauses

By Melissa Perkin. The recent High Court decision in Hellaby Resources Services Limited v Body Corporate 197281 [2021] NZHC 554 is of particular interest in the construction sector for several key reasons: it is a rare example where a stay of enforcement of summary...

The Enforceability of Liquidated Damages Clauses

Author: Melissa Perkin  Liquidated damages clauses, a common feature of construction contracts, stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered. A recent United Kingdom decision of the...

Building and Construction Under COVID-19 Alert Level 4

For information and guidance on what building and construction work can be done at Alert Level 4: ·       Health and Safety protocols at different alert levels, visit CHASNZ COVID-19 and working at the current alert level (chasnz.org); and ·       COVID-19 guidance...

Class-action lawsuit against Harditex cladding fails

By Melissa Perkin.  A second class-action lawsuit[1] brought by a group of 144 homeowners whose homes were clad in Harditex fibre-cement cladding, has failed. The homeowners alleged that Harditex manufacturer James Hardie, between 1987 – 2005, knowingly sold defective...

What types of disputes can be referred to adjudication?

The types of dispute that can be referred to adjudication are listed below:  Default liability claim These are claims for technical non-compliance with the payment regime under the Act. Where a valid payment claim has been served by a payee on a payer and the payer...

Proposed Changes to the Construction Retentions Regime

Author: Hannah Stanley, Building Disputes Tribunal Registrar Despite the introduction of the retentions regime into the Construction Contracts Act 2002 (the Act) in 2017[1], many subcontractor retentions have still been left unprotected and various gaps in the...

Show Me the Money: Seven Things to Remember When Preparing a Payment Claim

By Amy McDonald Are you still waiting on an invoice to be paid that you sent ages ago? Have you done all the work but have nothing to show for it? Unpaid invoices can have a devastating impact on builders and subcontractors. Fortunately, the Construction Contracts Act...

Experts’ duties and conflicting interests – Secretariat Consulting Pte Ltd v A Company

By Belinda Green. Experts may look to amend their terms of engagement, as the English Court of Appeal finds a conflict of interest clause applied to a global brand, despite involving separate experts in different locations, contracting via separate legal entities....

Payment Claims: using Xero to send out your invoices? Don’t forget the important notice

By Catherine Green.   Do you use Xero to send out your invoices? Make sure they are compliant payment claims under the Construction Contracts Act 2002 (Act). The default payment regime under the Act is an efficient and effective way of getting your invoices paid....

The Award of Enforcement Costs under the Construction Contracts Act 2002

By Melissa Lin and Nashi Ali. Payees intending to recover costs from payers during the course of legal proceedings may want to reconsider issuing a statutory demand in the first instance and seek an adjudicator’s determination instead. Cubo Projects Ltd v S&S...

When will (and won’t) implied warranties expand the scope of works?

By Maria Cole. The New South Wales Court of Appeal confirms statutory warranties can expand a scope of works, but the bargain that has been agreed to still holds sway. Oikos Constructions Pty Limited v Ostin [2020] NSWCA 358 (Oikos Constructions) In Oikos...

Bought a house – got problems – no one wants to know?

Author: Hannah Stanley, Building Disputes Tribunal Registrar As a homeowner, discovering structural defects in your home is the last thing you want and most wonder where to go from there in terms of their rights and how to remedy the situation. The Courts are often a...

Adjudication: calculating time over the Christmas period 2019-2020

What are the non-working days over the Christmas period this year?

The builder’s right to fix

Introduction When a dispute over defective building work turns ugly, the owner is sometimes tempted to refuse the builder the opportunity of returning to rectify the defects.  There are risks in this course.  This update considers a recent NSW Supreme Court decision...

Case In-Brief: Hybrid contracts and the payment provisions of the Construction Act

The Housing Grants, Construction and Regeneration Act 1998 (the Act) applies to “construction operations”. Where a contract relates to both “construction operations” and non-construction operations, the question arises of how payment mechanisms apply to construction...

When can you go to Adjudication?

Under section 25 of the Act, any party to a construction contract is entitled to refer a dispute arising under that construction contract to adjudication except where the parties have agreed to refer disputes between them to arbitration and the arbitration is an...

A brief introduction to Adjudication

What is adjudication? Adjudication is a unique fast track statutory dispute resolution process or resolving building and construction disputes under the Act. It is the most commonly used dispute resolution process for resolving such disputes. Adjudication is quick and...

Initiating Adjudication: The Notice of Adjudication

Initiating Adjudication: Back to Basics   Part One: The Notice of Adjudication The preparation of the Notice of Adjudication is arguably the most important step in the Adjudication process under the Construction Contracts Act (the Act). It is that document...

Initiating Adjudication: Service of the Notice of Adjudication

Initiating Adjudication: Back to Basics   Part Two: Service of the Notice of Adjudication You have your Notice of Adjudication prepared, but what steps do you need to take to serve it? This note sets out in brief the requirements for service under the...

Initiating Adjudication: Appointing an Adjudicator

Initiating Adjudication: Back to Basics Part Three: Appointing an Adjudicator Following on from Part Two of our three-part series on initiating adjudication, in this note we briefly look at how to appoint an adjudicator under the Construction Contracts Act (the Act)....