Arb-Med Model Clause

Ensure an effective and proportionate response in the future should a dispute arise
Model Clauses GuideContact Us

Arb-med is a hybrid dispute resolution process that combines the benefits of arbitration and mediation, including speed, procedural flexibility, confidentiality, choice of decision maker, ease of access to the tribunal, continuity, finality, and enforceability of the outcome.

The following arb-med clause should be included in contracts where the parties wish to have any future disputes resolved by Arb-Med under the Building Disputes Tribunal’s Arb-Med Rules:

“Any dispute or difference arising out of or in connection with this contract, or the subject matter of this contract, including any question about its existence, validity or termination, shall be referred to and finally resolved by arbitration in accordance with the Arb-Med Rules of the Building Disputes Tribunal.”

NOTE: parties to an existing dispute that have not incorporated the Building Disputes Tribunal Model Clause into a prior agreement may agree to refer that dispute to Arbitration under the Building Disputes Tribunal Arb-Med Rules by signing the Arb-Med Agreement in the form found at Appendix 2 to those Rules.

Download our complete guide to model clauses here as a pdf or read online below.

When you think the amount of your personal guarantee had a limit – but it didn’t.

In a recent Court of Appeal case, Cancian v Carters [2021] NZCA 397, Carters sought to enforce a personal guarantee against Mr Canican.  The Court dismissed an argument from Mr Cancian that Carters had not notified him that that the limit on his personal guarantee had...

BuildLaw Issue 44

December 2021CONTENTS Testing the waters: New South Wales Supreme Court considers the prevention principle Adjudication enforcement by companies in liquidation: Court of Appeal raises fundamental objections Wilful breaches of contract – Do exclusion clauses and...

Leaky Home Case: Failure to obtain a building report results in reduction of damages for contributory negligence

By Melt Strydom. Apportionment for contributory negligence allows a court to share the responsibility between parties in circumstances where the test for causation and remoteness of damage justifies it. It doesn’t mean a respondent will not be held liable for...

Do payment claims for retention money ‘fit’ with the standard terms of contract in New Zealand?

By Maria Cole The New Zealand Construction Contracts Act 2002 (CCA) does not explicitly state that payment claims can be used to recover retention money. That said, it is clear the 2015 amendments to the definition of a ‘payment’ under the CCA are broad enough to...

Resolving Construction Disputes – Is Adjudication a Good Option?

By Natalia Vila.   With few exceptions, the Construction Contracts Act 2002 (the Act) applies to every construction contract relating to construction work carried out in New Zealand. Statutory adjudication under the Act is the most commonly used dispute...

BuildLaw Issue 43

September 2021CONTENTS Construction contracts: enforcement of debts due and mandatory alternative dispute resolution clauses Cost certainty for resolving building and construction disputes: extension to the BDT Adjudication Low Value Claim scheme Engineers’ corner:...

“New build” residential property interest deductions rule clarified as new tax rules are set to apply from this Friday

The Government proposed changes to the rules that allowed property owners to claim interest on loans used for residential properties as an expense against their income from those properties. These rules are set to take effect in just three days, on 1 October 2021....

Cost certainty for resolving building and construction disputes: Extension to the BDT Adjudication Low Value Claim Scheme

By Belinda Green.   One of the main barriers to dispute resolution is cost: no one wants to risk spending more than the amount they recover. With inflation and construction costs always on the rise, BDT is extending its Low Value Claim (LVC) Scheme for...

Construction Contracts – Enforcement of Debts Due and Mandatory Alternative Dispute Resolution Clauses

By Melissa Perkin. The recent High Court decision in Hellaby Resources Services Limited v Body Corporate 197281 [2021] NZHC 554 is of particular interest in the construction sector for several key reasons: it is a rare example where a stay of enforcement of summary...

The Enforceability of Liquidated Damages Clauses

Author: Melissa Perkin  Liquidated damages clauses, a common feature of construction contracts, stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered. A recent United Kingdom decision of the...