by Virginia Bonanni | Apr 7, 2022 | Adjudication, Arbitration, Building, Construction, Contract law
By Sam Dorne Liability in tort depends upon proof of a personal breach of duty, with one true exception, vicarious liability. The law of negligence is generally fault based; a defendant is personally liable only for the defendant’s own negligent acts and omissions....
by Virginia Bonanni | Apr 7, 2022 | Adjudication, Arbitration, Building, Construction, Contract law
By Sam Dorne The decision in Hirst v Dunbar [2022] EWHC 41 (TCC) considers the impact of payment provisions in a construction contract, whether through contract or implied terms, and the commencement of the limitation period for payment claims under the contract. It...
by Virginia Bonanni | Apr 7, 2022 | Adjudication, Building, Construction
By Jo O’Dea In an extension of time claim, blame for the delay was a relevant consideration when assessing what was “fair and reasonable”. In CAJ v CAI [2021] 5 GCA 102, the Singapore Court of Appeal considered the issue of extensions of time in...
by Virginia Bonanni | Feb 25, 2022 | Adjudication, Building, Construction, Contract law
By Hannah Aziz Court provides further confirmation that the prevention principle can be excluded by the terms of a contract. Introduction Following our recent commentary comparing the operation of the prevention principle in New South Wales and Victoria, the...
by Virginia Bonanni | Feb 15, 2022 | Adjudication, Building, Construction, Payment claims
By Belinda Green Collateral warranties might be parasitic on a construction contract, but that doesn’t automatically mean they are one. The individual wording and circumstances need to be considered. In some cases, like in Toppan Holdings Limited v Simply Construction...
by Virginia Bonanni | Dec 22, 2021 | Adjudication, Building, Case Law, Construction, Contract law, Payment claims
In a recent Court of Appeal case, Cancian v Carters [2021] NZCA 397, Carters sought to enforce a personal guarantee against Mr Canican. The Court dismissed an argument from Mr Cancian that Carters had not notified him that that the limit on his personal guarantee had...
by Virginia Bonanni | Nov 1, 2021 | Adjudication, Building, Construction, Contract law, Payment claims
By Melt Strydom. Apportionment for contributory negligence allows a court to share the responsibility between parties in circumstances where the test for causation and remoteness of damage justifies it. It doesn’t mean a respondent will not be held liable for...
by Virginia Bonanni | Oct 29, 2021 | Adjudication, Building, Construction, Contract law, Payment claims
By Maria Cole The New Zealand Construction Contracts Act 2002 (CCA) does not explicitly state that payment claims can be used to recover retention money. That said, it is clear the 2015 amendments to the definition of a ‘payment’ under the CCA are broad enough to...
by Virginia Bonanni | Oct 21, 2021 | Adjudication, Building, Construction, Contract law, Initiating Adjudication
By Natalia Vila. With few exceptions, the Construction Contracts Act 2002 (the Act) applies to every construction contract relating to construction work carried out in New Zealand. Statutory adjudication under the Act is the most commonly used dispute...
by Virginia Bonanni | Sep 16, 2021 | Adjudication, Building, Construction, Payment claims
By Belinda Green. One of the main barriers to dispute resolution is cost: no one wants to risk spending more than the amount they recover. With inflation and construction costs always on the rise, BDT is extending its Low Value Claim (LVC) Scheme for...
by Virginia Bonanni | Sep 3, 2021 | Adjudication, Arbitration, Building, Construction, Contract law, Payment claims
By Melissa Perkin. The recent High Court decision in Hellaby Resources Services Limited v Body Corporate 197281 [2021] NZHC 554 is of particular interest in the construction sector for several key reasons: it is a rare example where a stay of enforcement of summary...
by Virginia Bonanni | Aug 25, 2021 | Adjudication, Building, Construction, Contract law, Payment claims
Author: Melissa Perkin Liquidated damages clauses, a common feature of construction contracts, stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered. A recent United Kingdom decision of the...