Early Neutral Evaluation Model Clause

Ensure an effective and proportionate response in the future should a dispute arise
Model Clauses GuideContact Us

Early Neutral Evaluation is a consensual, confidential and relatively informal process in which parties to a dispute use the services of an independent, neutral evaluator to provide a non-binding evaluation of the facts, evidence and legal merits of the matters in dispute.

The process is specifically designed for disputes which are already in litigation or arbitration. The key elements of Early Neutral Evaluation are that a dispute has already arisen, the parties are a long way apart and looking at lengthy court or arbitral proceedings. In such cases, the parties might benefit from an independent assessment or evaluation of the issues that have arisen and the likely outcome and range of damages if the matter is to proceed, to promote settlement discussions.

The parties may enter into an agreement for those purposes, and the following clause is recommended. The words in square brackets should be deleted/completed, as appropriate.

“[Name of first party] and [Name of second party and Ors] hereinafter referred to as the parties, are parties to [[a contract entered into on or about [enter date]] or [ proceedings in the [ ] Court referred to as CIV- ]].

 

The parties have agreed that all matters in dispute between them shall be referred to Early Neutral Evaluation by [Name of Evaluator] in accordance with the Agreement for Early Neutral Evaluation and Rules for Early Neutral Evaluation of the Building Disputes Tribunal (BDT) which procedures and rules are deemed to be incorporated by reference herein.

 

[if the parties are unable to agree upon the identity of an Evaluator within five (5) working days from the date of this agreement, then the Evaluator shall be appointed by BDT upon the application of any party.]”

Download our complete guide to model clauses here as a pdf or read online below.

When you think the amount of your personal guarantee had a limit – but it didn’t.

In a recent Court of Appeal case, Cancian v Carters [2021] NZCA 397, Carters sought to enforce a personal guarantee against Mr Canican.  The Court dismissed an argument from Mr Cancian that Carters had not notified him that that the limit on his personal guarantee had...

BuildLaw Issue 44

December 2021CONTENTS Testing the waters: New South Wales Supreme Court considers the prevention principle Adjudication enforcement by companies in liquidation: Court of Appeal raises fundamental objections Wilful breaches of contract – Do exclusion clauses and...

Leaky Home Case: Failure to obtain a building report results in reduction of damages for contributory negligence

By Melt Strydom. Apportionment for contributory negligence allows a court to share the responsibility between parties in circumstances where the test for causation and remoteness of damage justifies it. It doesn’t mean a respondent will not be held liable for...

Do payment claims for retention money ‘fit’ with the standard terms of contract in New Zealand?

By Maria Cole The New Zealand Construction Contracts Act 2002 (CCA) does not explicitly state that payment claims can be used to recover retention money. That said, it is clear the 2015 amendments to the definition of a ‘payment’ under the CCA are broad enough to...

Resolving Construction Disputes – Is Adjudication a Good Option?

By Natalia Vila.   With few exceptions, the Construction Contracts Act 2002 (the Act) applies to every construction contract relating to construction work carried out in New Zealand. Statutory adjudication under the Act is the most commonly used dispute...

BuildLaw Issue 43

September 2021CONTENTS Construction contracts: enforcement of debts due and mandatory alternative dispute resolution clauses Cost certainty for resolving building and construction disputes: extension to the BDT Adjudication Low Value Claim scheme Engineers’ corner:...

“New build” residential property interest deductions rule clarified as new tax rules are set to apply from this Friday

The Government proposed changes to the rules that allowed property owners to claim interest on loans used for residential properties as an expense against their income from those properties. These rules are set to take effect in just three days, on 1 October 2021....

Cost certainty for resolving building and construction disputes: Extension to the BDT Adjudication Low Value Claim Scheme

By Belinda Green.   One of the main barriers to dispute resolution is cost: no one wants to risk spending more than the amount they recover. With inflation and construction costs always on the rise, BDT is extending its Low Value Claim (LVC) Scheme for...

Construction Contracts – Enforcement of Debts Due and Mandatory Alternative Dispute Resolution Clauses

By Melissa Perkin. The recent High Court decision in Hellaby Resources Services Limited v Body Corporate 197281 [2021] NZHC 554 is of particular interest in the construction sector for several key reasons: it is a rare example where a stay of enforcement of summary...

The Enforceability of Liquidated Damages Clauses

Author: Melissa Perkin  Liquidated damages clauses, a common feature of construction contracts, stipulate the amount of money payable as damages for loss caused by a breach of contract, irrespective of the actual loss suffered. A recent United Kingdom decision of the...