By Hannah Aziz
Court provides further confirmation that the prevention principle can be excluded by the terms of a contract.
Introduction
Following our recent commentary comparing the operation of the prevention principle in New South Wales and Victoria, the Supreme Court of New South Wales has in MP Water Pty Ltd v Veolia Water Australia Pty Ltd[1] continued the line of authority that the application of the prevention principle can be excluded by the terms of a contract.
The facts
In November 2017 MP Water Pty Ltd (MP) entered into a Design and Construct Contract (the Contract) and a Services Provider Agreement (SPA) with Veolia Water Australia Pty Ltd (Veolia) for the operation and maintenance of a water treatment facility in Lithgow, New South Wales (the Facility).
In accordance with the SPA, Veolia was required to treat water delivered from two underground coal mines at the Facility. Veolia was also required to meet certain flow and capacity obligations as part of operating the water treatment system, including the continuous and uninterrupted acceptance of the water from the coal mines at an agreed rate, with capacity for occasional acceptance of the water at a higher rate (the Guarantees). If the Guarantees were not met, they could be deemed a major service failure. Any major service failure would entitle MP to issue default notices.
Deficiencies were identified in an existing storage pond, and MP undertook to rectify the deficiencies. Veolia advised that it could not meet the Guarantees without the storage ponds operating at their promised capacity. On 7 May 2021 the Facility failed to process and accept water from the mines for 48 hours.
MP issued a default notice on 11 May 2021 in relation to that failure on the basis that it constituted a major service failure under the Contract. MP issued a direction requiring Veolia to remedy the alleged default by 12 pm on 12 May 2021. MP also issued a step-in notice. Veolia rejected the step-in notice as unlawful. Veolia argued that it was unable to provide the services because MP had failed to rectify the deficiencies in the storage pond. On this basis, Veolia argued that the prevention principle was enlivened and thus precluded MP from relying on the default notice.
The decision
Justice Williams held that the prevention principle has two elements:
- wrongful conduct (assessed by reference to the terms of the contract); and
- the consequences of wrongful conduct.
She also held that the operation of the prevention principle may be modified or excluded by contract. Justice Williams held that this was just such a situation as the SPA excluded the operation of the prevention principle. As the contract required only the mere existence of a relevant service failure for a default notice to be issued, the rationale behind why the service was not provided was immaterial.
Conclusion
This decision provides further confirmation of New South Wales’ expansive approach in considering the operation of the prevention principle, particularly when compared to that of its neighbour, Victoria. This case serves as an important reminder to parties when considering the drafting of contracts. The prevention principle can be excluded by virtue of clear, well-drafted contractual terms.
[1] (No 3) [2021] NSWSC 1023.
Vicarious liability and subcontractors
Limitation for payment claims under construction contracts
Extensions of time in construction contracts
BuildLaw Issue 45
Construction contract or product warranty? Not all collateral warranty disputes can be adjudicated
When you think the amount of your personal guarantee had a limit – but it didn’t.
BuildLaw Issue 44
Leaky Home Case: Failure to obtain a building report results in reduction of damages for contributory negligence
Do payment claims for retention money ‘fit’ with the standard terms of contract in New Zealand?
Resolving Construction Disputes – Is Adjudication a Good Option?
BuildLaw Issue 43
Cost certainty for resolving building and construction disputes: Extension to the BDT Adjudication Low Value Claim Scheme
Construction Contracts – Enforcement of Debts Due and Mandatory Alternative Dispute Resolution Clauses
The Enforceability of Liquidated Damages Clauses
Building and Construction Under COVID-19 Alert Level 4
Class-action lawsuit against Harditex cladding fails
What types of disputes can be referred to adjudication?
Important Guidance on Contract Interpretation Issued by the Supreme Court
What are the cost implications of challenging an arbitral award through the courts?
Proposed Changes to the Construction Retentions Regime
Show Me the Money: Seven Things to Remember When Preparing a Payment Claim
BuildLaw Issue 42
Overhaul of Resource Management System
Experts’ duties and conflicting interests – Secretariat Consulting Pte Ltd v A Company
Payment Claims: using Xero to send out your invoices? Don’t forget the important notice
The Award of Enforcement Costs under the Construction Contracts Act 2002
High-Risk Cladding Banned In Multiple Jurisdictions
When will (and won’t) implied warranties expand the scope of works?
BuildLaw Issue 41
Construction Disputes – Are they on the rise?
BuildLaw Issue 40
Bought a house – got problems – no one wants to know?
Assessing sums payable in the absence of a contract: Electrix Limited v The Fletcher Construction Company Limited [2020] NZHC 918
BuildLaw Issue 39
BuildLaw Issue 38
Adjudication: calculating time over the Christmas period 2019-2020
The builder’s right to fix
The ‘collaborative’ future of construction and infrastructure procurement
Case In-Brief: Hybrid contracts and the payment provisions of the Construction Act
BuildLaw Issue 37
The Supreme Court reinstatement is not a right that can be assigned
Contractual appendices: ignore at your peril
New Government Procurement Rules Announced (4th Edition)
Building Law reforms: Raising the bar across the sector
BuildLaw Issue 36
BuildLaw Issue 35
When can you go to Adjudication?
Alliancing: what does the new NEC4 Alliance Contract have to offer?
BuildLaw Issue 34
Neutral Evaluation Revisited
Recent Posts
- And you think you may have problems with your construction contract?
- Vicarious liability and subcontractors
- Limitation for payment claims under construction contracts
- Extensions of time in construction contracts
- Construction contract procedure and dispute resolution: There really is a reason to pay attention to the boring stuff
Archives
- April 2022
- March 2022
- February 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- April 2021
- March 2021
- November 2020
- September 2020
- June 2020
- May 2020
- December 2019
- November 2019
- August 2019
- July 2019
- May 2019
- April 2019
- March 2019
- January 2019
- December 2018
- November 2018
- June 2018
- May 2018
- March 2018
- December 2017
- September 2017
- June 2017
- March 2017
- December 2016
- September 2016
- June 2016
- March 2016